13.2 C
London
Wednesday, October 30, 2024

Tanzania boosts rural villages with 2.4 MW wind farm

More News

- Advertisement -

Tanzania is expected to celebrate the opening of its first wind farm next month, when a 2.4-MW wind power facility will finish testing and begin supplying the customers of a rapidly expanding private rural grid network.

Once operational, the wind farm will provide much-needed energy security to customers of a rapidly expanding private rural grid network developed and operated by project developer Rift Valley Energy Group.

The farm’s three turbines have recently arrived at the project site in Mwenga in the Mufindi District of Tanzania’s Iringa region, and installation and testing is expected to be completed by early May.

The rural grid network is currently powered by a 4MW hydropower plant that has been operational since 2012, and is the first private large-scale rural network in Tanzania.

The plant provides clean, grid-quality electricity to more than 4,500 homes and businesses across 32 villages, including energy-intensive end users such as tea-processing companies and sawmills, as well as the region’s rapidly growing SME sector. Any surplus power is sold to TANESCO under a power purchase agreement.

The new wind farm will enable the planned expansion of the rural network to continue, which is expected to connect a further 1,500 customers over the next two years, and counter the hydro plant’s varying output due to the region’s seasonality of rainfall.

The business model behind the hybrid development represents an innovative energy solution for the region, since it is led by the private sector and combines multiple generation sources and offtakes – including that of the national utility – at a large scale.

Geoff Sinclair, Managing Director of Camco Clean Energy, REPP’s investment manager, said: “Complementing the existing hydro plant with a wind farm is a smart move that will enable Rift Valley to greatly improve the quality and reliability of its rural grid network, which has already had a transformational impact on thousands of homes and businesses in Tanzania.

“The success of the project should have a strong demonstration effect in other countries and provide a replicable solution for complex power supply issues elsewhere in Africa.”

Michael Gratwicke, Managing Director of Rift Valley Energy, said: “The REPP facility has been critical to concluding the financial structure for the project, and provides the project with the necessary risk reduction mechanisms to best manage the anticipated rapid evolution of our associated growing rural distribution markets.”

To date, the project has created approximately 50 temporary jobs during construction, and will create a further six permanent positions for people from the surrounding area during operation.

Also read

Africa Union and IRENA to advance renewables in response to Covid-19

- Advertisement -

LEAVE A REPLY

Please enter your comment!
Please enter your name here

GET MORE LEADS WITH CCE NEWS

Discover amazing advertising opportunities on CCE NEWS and get 20% off for your first advert. Click below:

MAGAZINE

Projects

Top Events